Adani Green Energy Builds World’s Largest Renewable Energy Park in Khavda, Gujarat

Adani Green Energy Limited, an Adani Group company, is building the world’s largest renewable energy park in Khavda, Kutch district of Gujarat. The park is spread over 538 square kilometers, which is about five times larger than the total size of the French capital, Paris.

Khavda Plant Capacity

  • According to Vineet Jain, Managing Director of Adani Green Energy, the total capacity of the Khavda plant will be 30 GW.
  • Adani Group will invest Rs 1.5 lakh crore in this project.
  • Currently, 2 GW of renewable energy is being produced from this park, and 4 GW capacity will be added by March 2025.
  • Thereafter, 5 GW capacity will be increased every year.

Khavda Park’s Proximity to the Pakistan Border

  • The Khavda Park is just 1 kilometer away from the international border with Pakistan.
  • The share of solar energy in the proposed capacity of 30 GW is 26 GW, while wind energy will be 4%.
  • When the park is fully operational, it will generate 81 billion units of electricity, which can supply the entire demand of countries like Belgium, Chile, and Switzerland.

Nodal Agency for Hybrid Renewable Energy Park

  • Gujarat Industries Power Company Limited (GIPCL) has been appointed as the nodal agency for the Hybrid Renewable Energy Park.
  • The project to build this park was prepared as part of Prime Minister Modi’s efforts to reduce carbon emissions, and work on the project has been ongoing since 2021.

Reasons for Locating the Hybrid Renewable Energy Park in Kutch

  • More than 1 lakh hectares of barren land is available near Khavda, located on the India-Pakistan border in Kutch, Gujarat.
  • The weather in this region is favorable for both solar and wind energy generation.
  • The area is sensitive from a security perspective, and permission was sought from the Defense Ministry to construct the park.

Challenges in Constructing the Hybrid Renewable Energy Park

  • Challenges include humid air, salty water, salty soil, and security concerns due to the park’s proximity to the Pakistan border.
  • Lack of basic facilities, including mobile networks, makes it difficult to retain workers on the project.
  • There is a risk of Pakistani terrorists infiltrating the worker population.

Timeline for Completion of the Hybrid Renewable Energy Park

  • 50% of the work will be completed by December 2024, with the production of 14,000 MW of electricity.
  • The Hybrid Renewable Energy Park will be fully operational by December 2026, with the production of 30 GW of electricity.

Sumit Arora

As a team lead and current affairs writer at Adda247, I am responsible for researching and producing engaging, informative content designed to assist candidates in preparing for national and state-level competitive government exams. I specialize in crafting insightful articles that keep aspirants updated on the latest trends and developments in current affairs. With a strong emphasis on educational excellence, my goal is to equip readers with the knowledge and confidence needed to excel in their exams. Through well-researched and thoughtfully written content, I strive to guide and support candidates on their journey to success.

Recent Posts

Bihar-Based Women’s Movement Gets Global Recognition at UN SDG Action Awards 2026

The film titled ‘Mothers of Courage’ has been awarded the United Nations SDG Action Award…

21 minutes ago

International Day for Biosphere Reserves 2026: Date, Significance, UNESCO and India’s 13 Biosphere Reserves

The International Day for Biosphere Reserves is celebrated every year on 3rd November. This was…

37 minutes ago

Prema Rawat Sets Women’s T20 Fastest-Fifty Record: 14-Ball Half-Century

Prema Rawat, a player from the Uttarakhand team made history by scoring the fastest half-century…

1 hour ago

Dhinidhi Desinghu Wins Historic Bronze at Dakar 2026 Youth Olympics, Becomes First Indian Swimmer to Medal

Indian swimmer Dhinidhi Desinghu created history by winning the bronze medal in the Women's 100m…

2 hours ago

Centre Extends Nandan Nilekani-Led Exam Reform Task Force Tenure Until January 2027

The tenure of the high-powered task force, led by Nandan Nilekani to reform the examination…

3 hours ago

VB-G RAM G Act Grievance Redressal Rules 2026: 15-Day Deadline for Complaints

The Centre has notified the VB-G RAM G Grievance Redressal Rules of 2026, it sets…

3 hours ago